The Park — Zones & Timeline
100 acres. Ten specialised zones. A 13-month construction timeline from first funding to grand opening.
Ten Specialised Zones
128 acres of thoughtfully designed spaces — every season will be peak season.
Schematic representation — not to scale
Implementation Timeline
✓ DoneDam 75% earthworks done, 2,500 trees planted, 2 boreholes drilled, roads cleared, drone mapping complete
Dam spillway, perimeter fencing (6.21km), entrance gate, solar borehole mechanisation
Fish pond, water fountain, lawn seeding, flower nursery establishment
All 6 botanical zones planted with drip irrigation from reservoir
Jetty, boat procurement, ticketing pavilion, restrooms, solar path lighting
Café & restaurant, amphitheatre, children's play area, ornamental bridge
Soft opening for invited guests, media, and investors
Official grand opening — full revenue-generating operations